Tracking Green Hydrogen Projects - Integrated Wind and Solar Power Hydrogen Production Project in Jarud Banner, Inner Mongolia Granted Record Filing

  • Sep 01, 2025, at 2:54 pm

Recently, the Zalut Banner Wind and Solar Power Hydrogen Production Integration Project of Inner Mongolia Jin ESS Investment New Energy Co., Ltd. has been approved for filing.

The project is located in the Chemical Industry Concentration Zone of Lubei Industrial Park, Zalut Industrial Park, Zalut Banner, Tongliao City, with a total investment of 2.98 billion yuan. The project owner is Inner Mongolia Jin ESS Investment New Energy Co., Ltd.

The project covers an area of 250 mu. It will construct 32 sets of green electricity off-grid hydrogen production alkaline electrolyzers, each with a capacity of 1,000 Nm³, along with 8 sets of 4,000 Nm³ gas-liquid separation and purification units. Supporting facilities include a circulating water station, initial rainwater pool, emergency pool, chilled water station, and other utility projects. Auxiliary production facilities such as a central control room, comprehensive warehouse, and laboratory building will also be constructed. The annual hydrogen production capacity is 126 million cubic meters.

The planned construction period is from May 2025 to April 2027.

Project details are as follows:

Project Filing Notification Amendment

Project Code: 2410-150526-04-01-743638

Project Owner: Inner Mongolia Jin ESS Investment New Energy Co., Ltd.

The energy project filing application for the Zalut Banner Wind and Solar Power Hydrogen Production Integration Project submitted by Inner Mongolia Jin ESS Investment New Energy Co., Ltd. complies with industrial policies and market access standards and is hereby approved for filing. Please proceed with relevant work accordingly. Before commencement of construction, other legally required procedures must be completed.

Construction Location: Chemical Industry Concentration Zone of Lubei Industrial Park, Zalut Industrial Park, Zalut Banner, Tongliao City

Total Investment: 2.98 billion yuan, including self-owned funds: 596 million yuan, bank loan application: 2.384 billion yuan, and others: 0 yuan

Planned Construction Period: May 2025 to April 2027

Construction Scale and Content: The project covers an area of 250 mu. It will construct 32 sets of green electricity off-grid hydrogen production alkaline electrolyzers, each with a capacity of 1,000 Nm³, along with 8 sets of 4,000 Nm³ gas-liquid separation and purification units. Supporting facilities include a circulating water station, initial rainwater pool, emergency pool, chilled water station, and other utility projects. Auxiliary production facilities such as a central control room, comprehensive warehouse, and laboratory building will also be constructed. The annual hydrogen production capacity is 126 million cubic meters.

Additional Notes: This filing serves only as a notification. If the project fails to comply with regulations of other departments or industries, the filing will automatically become invalid. Strictly adhere to regulations of relevant departments and promptly complete necessary procedures; otherwise, construction may not commence. Submit construction progress updates via the project reporting platform as per schedule. Energy conservation review procedures must be completed before construction begins.

(Note: If the project does not commence construction or complete any other procedures within 2 years of filing, the project owner must provide an explanation via the online platform if intending to continue the project. If no longer intending to proceed, apply to revoke the filed project. If neither action is taken after 2 years, the filing authority will delete the filed project and announce it on the online platform.)

Development and Reform Commission of Jarud Banner

29 Aug 2025