On August 5th, Gemeng Yihe New Energy Co., Ltd. launched tenders for the procurement of complete hydrogen production equipment and the EPC (Engineering, Procurement, and Construction) general contracting for the hydrogen production end of the Chayouqianqi Wind and Solar Power to Hydrogen Production Integrated Project (Phase I).
According to the "Tender Notice for the Procurement of Complete Hydrogen Production Equipment for the Hydrogen Production End of the Chayouqianqi Wind and Solar Power to Hydrogen Production Integrated Project (Phase I) by Gemeng Yihe New Energy Co., Ltd.", the project is located in Chahar Right Wing Front Banner, Ulanqab City, Inner Mongolia Autonomous Region. The construction scale includes an electrolytic water hydrogen production device with a rated hydrogen production capacity of 9000Nm³/h and a maximum hydrogen production capacity of 10800Nm³/h.
The Chayouqianqi Wind and Solar Power to Hydrogen Production Integrated Project is divided into a new energy end (including transmission lines and energy storage) and a hydrogen production end. It is proposed to adopt an off-grid hydrogen production method, utilizing 50MW of wind power for hydrogen production, mainly including:
New Energy End: A new energy installed capacity of 50MW of wind power, with an electrical energy storage scale tentatively set at 5MW/20MWh of all-vanadium redox flow batteries (the bidder may optimize the energy storage configuration scale under the premise of meeting the project's economic, efficient, safe, and stable operation requirements, and attach the configuration plan as an appendix, but it will not be included in this quotation), transmission lines, and necessary public auxiliary engineering and supporting facilities for wind power and energy storage;
Hydrogen Production End: A 35kV prefabricated cabin-type switch station, complete equipment for IGBT rectifier power supplies, complete equipment for PEM water electrolysis hydrogen production, an integrated control platform for green electricity hydrogen production, hydrogen filling devices, hydrogen storage facilities, and necessary public auxiliary engineering and supporting facilities.
As an equipment integration project, the tender scope includes (but is not limited to): 1) Complete equipment for a 35kV prefabricated cabin-type switch station; 2) Complete equipment for IGBT rectifier power supplies; 3) Complete equipment for a PEM water electrolysis hydrogen production system; 4) Complete equipment for an integrated control platform for green electricity hydrogen production.
Delivery Date: Deliver the first set of PEM equipment and complete public utility system equipment within three and a half months after the contract is signed, and complete the delivery of all equipment within four and a half months.
This section does not accept joint venture bids.
According to the "Tender Notice for the EPC General Contracting of the Hydrogen Production End of the Chayouqianqi Wind and Solar Power to Hydrogen Production Integrated Project (Phase I) by Gemeng Yihe New Energy Co., Ltd.":
This tender is divided into four sections: concentrated procurement of wind turbine generators and their ancillary equipment (Section A), EPC general contracting for the new energy part of the Chayouqianqi Wind and Solar Power to Hydrogen Production Integrated Project (Section B), procurement of complete hydrogen production equipment for the hydrogen production end of the Chayouqianqi Wind and Solar Power to Hydrogen Production Integrated Project (Phase I) (Section C), and the EPC project for the hydrogen production end of the Chayouqianqi Wind and Solar Power to Hydrogen Production Integrated Project (Section D).
The tender scope indicates that for the complete set of IGBT rectifier power supply equipment: 10 sets of 35kV power transformers and 20 sets of IGBT rectifier power supplies will be configured.
For the complete set of PEM water electrolysis hydrogen production system equipment: 36 sets of 250Nm³/h PEM electrolyzers, 9 sets of gas-liquid separation systems, 5 sets of hydrogen purification and drying systems, a pure water unit (for water storage and supply), a cooling unit (for cooling water and chilled water), etc., will be configured.
The planned construction period: The project is scheduled to commence on September 1, 2025, with the actual commencement date subject to the date specified in the notice to commence work issued by the employer or supervisor. System commissioning is to be completed by March 31, 2026, and the project will enter the trial operation phase.
Consortium bidding is accepted for this section.
The tender announcement is as follows:
Tender Announcement for the Procurement of Complete Hydrogen Production Equipment for the Chayouqianqi Wind and Solar Power Hydrogen Production Integrated Project (Phase I) of Gemeng Yihe New Energy Co., Ltd.
(Tender No.: GMZB-2025-08-004)
1. Tender Conditions
The tender project for the procurement of complete hydrogen production equipment for the Chayouqianqi Wind and Solar Power Hydrogen Production Integrated Project (Phase I) of Inner Mongolia Gemeng Yihe New Energy Co., Ltd. (Tender Project No.: M1401010786000378001) has its project funds sourced from enterprise self-financing. The bid inviter is Inner Mongolia Gemeng Yihe New Energy Co., Ltd. This project has met the tender conditions and is now open for public tendering.
2. Project Overview and Tender Scope
2.1 Construction Location: Located in Chahar Right Wing Front Banner, Ulanqab City, Inner Mongolia Autonomous Region.
2.2 Construction Scale: An electrolytic water hydrogen production plant with a rated hydrogen production capacity of 9000Nm³/h and a maximum hydrogen production capacity of 10800Nm³/h.
2.3 Delivery Date: The first set of PEM equipment and the complete set of utility system equipment are to be delivered within three and a half months after the contract signing, and all equipment deliveries are to be completed within four and a half months. The final delivery date is subject to the notice from the bid inviter.
2.4 Project Introduction: The Chayouqianqi Wind and Solar Power Hydrogen Production Integrated Project is divided into a new energy section (including transmission lines and energy storage) and a hydrogen production section. It is proposed to adopt an off-grid hydrogen production method, utilizing 50MW of wind power for hydrogen production. The project mainly includes:
New Energy Section: A new energy installed capacity of 50MW of wind power, with an electrical energy storage capacity tentatively set at 5MW/20MWh of all-vanadium redox flow batteries (the bidder may optimize the energy storage configuration scale under the premise of meeting the project's economic, efficient, safe, and stable operation requirements, and attach the configuration plan as an appendix, but it will not be included in this quotation), transmission lines, necessary public auxiliary engineering, and supporting facilities for wind power and energy storage.
Hydrogen Production Section: A 35kV prefabricated cabin-type switch station, complete sets of IGBT rectifier power supply equipment, complete sets of PEM water electrolysis hydrogen production equipment, an integrated green electricity hydrogen production control platform, hydrogen filling devices, hydrogen storage facilities, and necessary public auxiliary engineering and supporting facilities.
2.5 Scope of this tender:
001 No section division
As an equipment integration project, the scope includes (but is not limited to):
1) Complete equipment for 35kV prefabricated cabin-type switchgear station;
2) Complete equipment for IGBT rectifier power supply;
3) Complete equipment for PEM water electrolysis hydrogen production system;
4) Complete equipment for integrated green electricity hydrogen production control platform.
The bidder shall be responsible for the supply, installation guidance, commissioning, after-sales service, training, and other related work within the scope of this tender for the Chayouqianqi Wind and Solar Power Integrated Hydrogen Production Project. To ensure equipment performance and quality, the main equipment purchased by the bidder shall not be produced by enterprises on the bid inviter's list of unqualified suppliers.
3. Bidder qualification requirements
3.1 Basic qualification requirements
3.1.1 The bidder must be registered within the territory of the People's Republic of China, possess the ability to independently bear civil liability, and have corresponding service capabilities in professional technology, quality and safety management control, and business management.
3.1.2 The bidder must have sales performance of at least one set of PEM water electrolysis hydrogen production equipment with a hydrogen production capacity of 200Nm³/h or above per electrolyzer in the past five years (contract proof documents must be provided, with the contract signing time as the basis);
3.1.3 Reputation requirements: The bidder must have good credit standing and business reputation, not have undergone statutory dissolution or be in a state of suspension or bankruptcy, and its assets must not have been reorganized, taken over, or frozen. Audited financial reports for the past three years must be provided;
3.1.4 The bidder must not be listed on the "Dishonest Persons Subject to Enforcement" list on the "Credit China" website, not be listed on the "List of Enterprises with Serious Illegal and Dishonest Acts" on the National Enterprise Credit Information Publicity System, and have no record of bribery crimes as queried on the "China Judgment Documents Network";
3.1.5 Different units with the same person in charge or legal representative, or with controlling or management relationships, shall not participate in this tender project simultaneously;
3.1.6 Bidders with adverse credit records or listed on the blacklist of the Gemeng Group shall not participate in the bidding.
3.2 Special qualification requirements:
3.2.1 Production capacity requirements
Production facilities: The bidder must possess a specialized PEM electrolyzer production line and provide proof of ownership of the production facilities and capacity verification documents.
Production capacity: The bidder shall have at least one year or more of PEM electrolyzer production experience, possess a production capacity with a hydrogen production capacity per PEM electrolyzer of not less than 250Nm³/h, and be able to provide relevant proof materials, such as production and operation reports in recent years, sales contracts for PEM electrolyzer products, and customer usage feedback.
Testing capabilities: Bidders must have a dedicated PEM electrolyzer testing workshop and provide a list of testing equipment, copies of equipment purchase invoices, equipment calibration certificates, and other supporting materials.
3.2.2 Technical Specifications and Testing Reports
Bidders are required to provide detailed technical specifications for the PEM electrolyzer, including hydrogen production capacity, electrolysis energy consumption, electrolysis voltage, etc., and provide the calculation basis, design principles, and relevant technical documentation for the technical specifications.
Bidders must submit complete polarization curve testing reports, durability testing reports, start-up and shutdown characteristic testing reports, etc., in accordance with the requirements of the tender documents.
3.2.3 This section does not accept joint bidding;
3.2.4 Other requirements: Supporting materials such as independent production capacity, electrolyzer testing capabilities, technical specifications and testing reports, and performance records of subsidiaries with more than 50% shareholding can also be used as supporting materials for the parent company in the above-mentioned aspects.
4. Acquisition of Tender Documents
Acquisition period: From 19:00 on August 5, 2025, to 19:00 on August 15, 2025
Acquisition method: Online acquisition through the Shanxi Xindian Tendering and Bidding Trading Platform (http://www.sxxindian.com)
5. Submission of Bidding Documents
Submission deadline: 09:30 on August 27, 2025
Submission method: Upload encrypted electronic bidding documents to the website (http://www.sxxindian.com) before the submission deadline.
Submission address: Shanxi Xindian Tendering and Bidding Trading Platform (http://www.sxxindian.com)
6. Bid Opening Time and Location
Bid opening time: 09:30 on August 27, 2025
Bid opening method: Online bid opening
7. Forms of Bid Security Submission
For this project, bid security can be submitted in non-cash transaction guarantee forms such as wire transfers, bank guarantees, guarantee insurance, guarantee institution guarantees, electronic guarantees, etc.
8. Channels and Methods for Raising Objections
Channels for raising objections: Through the electronic tendering and bidding trading platform (system)
Contact person for receiving objections: Ms. Shi
Telephone: 0351-7815241
9. Other Announcement Contents
(1) This tender announcement is simultaneously published on the "Shanxi Province Tendering and Bidding Public Service Platform" and the "Shanxi Xindian Tendering and Bidding Trading Platform".
(2) The selling price of the tender documents is as follows (non-refundable): 1,000 yuan. Ordinary invoices will be issued for the tender document fees, and the tendering agency will send electronic invoices to the email address provided during bid registration after the bid opening.
After paying the fee for the tender documents, interested bidders shall upload the "Payment Voucher" and the attached "Mailing Information Form for the Letter of Acceptance" through the Shanxi Xindian Tendering and Bidding Trading Platform (http://www.sxxindian.com), and after paying the platform usage fee, download the tender documents;
The bank account information of the agency company is as follows (only accepting company-to-company account transfers):
Account Name: Shanxi Gemeng Sino-US Clean Energy R&D Center Co., Ltd.
Bank: Pudong Development Bank, Beidajie Branch, Taiyuan City, Shanxi Province
Account Number: 68140154700000801
Bank Code: 310161000101
(3) This tender is a full-process online tendering project. Bidding units must register in the Shanxi Province Bidders' Database and obtain a CA certificate for online bidding. (Electronic CA keys are not required during the bid document purchase phase.)
Note: 1. All interested bidders must register in the "Trading Market Entities Database" section of the National Public Resources Trading Platform (Shanxi Province) (website: http://prec.sxzwfw.gov.cn/). For details, please refer to the registration guide for the Trading Market Entities Database (website: http://jyzt.sxzwfw.gov.cn/ztxxzc/index.jhtml).
2. If you need to obtain a CA digital certificate, please refer to the "Digital Certificate Cross-Recognition" section of the National Public Resources Trading Platform (Shanxi Province) (website: http://prec.sxzwfw.gov.cn/) (website: http://prec.sxzwfw.gov.cn/cajchrpt/).
Consultation hotline for CA certificate application: 0351-6655773
Platform customer service hotline: 0351-8063868
Platform contact person's hotline: 18534576528 (Working hours: 9:00-12:00, 13:30-18:00)
10. Supervisory Department
The supervisory department for this tendering project is the Shanxi Provincial Energy Administration and Shanxi International Energy Group ESS Co., Ltd.
Tel: 0351-7850578
Email: lijin@gmgjny.com
11. Contact Information
Bid Inviter: Inner Mongolia Gemeng Yihe New Energy Co., Ltd.
Address: Dongmeng East Road, Tianpishan Metallurgical and Chemical Industry Park, Chahar Right Front Banner, Ulanqab City, Inner Mongolia Autonomous Region, north of Xingba Expressway
Contact Person: Mr. Guo
Contact Number: 15525468701
Email: 1962420937@qq.com
Tendering Agency: Shanxi Gemeng Sino-US Clean Energy R&D Center Co., Ltd.
Address: Building 2, Shanxi Gemeng Sino-US Clean Energy R&D Center Co., Ltd. (100 meters east of the intersection of Zhengyang Street and Malianying Road, Taiyuan City)
Contact Person: Ms. Shi
Tel: 0351-7815241
Email: 54400111@qq.com
Tender Notice for EPC General Contracting of the Hydrogen Production End of the Chahar Right Front Banner Wind and Solar Power Hydrogen Production Integrated Project (Phase I) of Gemeng Yihe New Energy Co., Ltd.
(Tender Number: GMZB-2025-08-005)
I. Tender Conditions
This EPC general contracting project for the hydrogen production end of the Chahar Right Front Banner Wind and Solar Power Hydrogen Production Integrated Project (Phase I) of Inner Mongolia Gemeng Yihe New Energy Co., Ltd. (Tender Project Number: M1401010786000378002) is funded by enterprise self-financing and bank loans. The bid inviter is Gemeng Yihe New Energy Co., Ltd. The project has met the tendering conditions and is now open for public tendering.
II. Project Overview and Tendering Scope
1. Project Introduction:
Project I Introduction: The Chayouqianqi Wind and Solar Power to Hydrogen Integrated Project is divided into a new energy section (including transmission lines) and a hydrogen production section (energy storage). It is planned to adopt an off-grid hydrogen production method, utilizing 50MW of wind power for hydrogen production. The project mainly includes:
New Energy Section: A new energy installation capacity of 50MW of wind power, installation of 8 wind turbines with a capacity of 6.25MW each, an initial electrical energy storage capacity of 5MW/20MWh, two 35kV transmission lines, wind power, and necessary public auxiliary projects and supporting facilities;
Hydrogen Production Section: A water electrolysis hydrogen production unit with a rated hydrogen production capacity of 9000Nm³/h and a maximum hydrogen production capacity of 10800Nm³/h. A 35kV prefabricated container-type switch station, complete sets of IGBT rectifier power supply equipment (including power transformers), complete sets of electrolytic hydrogen production equipment (including separation and purification), an integrated green electricity to hydrogen production control platform, an energy storage system (with an initial capacity of 5MW/20MWh), a water production system, compressors, hydrogen filling devices, hydrogen storage facilities, and necessary public auxiliary projects and supporting facilities.
Project II Introduction: The project involves the procurement of wind turbine generators and their ancillary equipment required for the Green Power Supply Project (Phase I) in the Mingantu Industrial Park of the Xilingol Industrial Development Zone undertaken by Gemeng Nuojin New Energy Co., Ltd. The planned installed capacity is 100MW, with a single unit capacity of 6.25MW, totaling 16 sets. This project only involves the procurement of wind turbines and towers.
This tender is divided into four sections: centralized procurement of wind turbine generators and their ancillary equipment (Section A), EPC general contracting for the new energy section of the Chayouqianqi Wind and Solar Power to Hydrogen Integrated Project (Section B), procurement of complete sets of equipment for the hydrogen production section of the Chayouqianqi Wind and Solar Power to Hydrogen Integrated Project (Phase I) (Section C), and EPC project for the hydrogen production section of the Chayouqianqi Wind and Solar Power to Hydrogen Integrated Project (Section D).

2. Tendering Content and Scope:
001 No section division. The tendering scope for this tender is Section D mentioned above, and the main tendering content includes:
(1) The planning and design, supplementary survey (if necessary), preliminary design, construction drawing design, as-built drawing design, three-dimensional design of the entire plant, BIM model design, and technical documentation for the procured equipment and materials for the entire hydrogen production section of this project.
(2) The procurement, supervision (if necessary), installation, commissioning of equipment and materials, single unit test run, coordination of combined test run and commissioning with feedstock, testing, acceptance, establishment of the delivery site yard, transportation, unloading, storage, and other related work for this project.
(3) Construction and installation, commissioning, and services during the warranty period, as well as construction management for this project, project engineering insurance (excluding all-risk insurance for the project engineering and third-party liability insurance), and the implementation of approved supervision and monitoring plans for soil and water conservation and environmental protection.
(4) Complete all the formalities with government industry authorities (units) such as the quality supervision, special inspection, and land and resources departments for this construction project.
(5) Architectures, equipment, materials, and services that are not explicitly listed in the tender documents but are essential for the function, safety, and stable operation of this construction project, and that meet the requirements for the safe operation of the national, local government, and industry authorities (such as regulatory departments, power supply departments, and the employer's system), as well as the completion acceptance requirements of the state and Shanxi International Energy Group.
For detailed tender scope, refer to the relevant sections of the tender documents.
3. Contractor Mode: EPC General Contracting Mode
4. Construction Location: Chahar Right Front Banner, Ulanqab City, Inner Mongolia
5. Planned Construction Period: September 1, 2025. The actual commencement date shall be subject to the date specified in the commencement notice issued by the employer or the supervisor. System commissioning shall be completed before March 31, 2026, and the project shall enter the trial operation stage.
6. Quality Standards:
Conform to the current relevant national and industry standards (see technical clauses for details).
III. Bidder Qualification Requirements
1. The bidder shall have independent legal person status in the People's Republic of China;
2. The bidder shall simultaneously possess:
(1) Grade A comprehensive qualification for engineering design or Grade A or above qualification for engineering design in the chemical, petrochemical, and pharmaceutical industries;
(2) Grade I or above qualification for general contracting of construction engineering and Grade I qualification for general contracting of mechanical and electrical engineering, and shall have a valid safety production license.
3. The bidder shall have at least one hydrogen production engineering contracting performance from January 1, 2020, to the bid submission deadline (based on the contract check-in time). Copies of contracts (at least providing the first page, subject page, and signature page of the contract, with the main construction content, signing date, and contract amount reflected in the scanned copy of the original contract), project acceptance certificates (project completion acceptance certificates), or supporting documents issued by the owner shall be provided for the above-mentioned performances. If the above-mentioned supporting documents are not provided or the provided performance supporting documents cannot confirm the performance, it shall be deemed as invalid performance.
4. The proposed project manager of the bidder shall simultaneously meet the following requirements:
(1) Possess the practicing qualification of a registered chemical engineer or a first-level registered construction engineer (in the mechanical and electrical engineering discipline);
(2) Possess a "Safety Production Assessment Certificate" (Category B) issued by administrative authorities at or above the provincial level;
(3) Not serve as the project manager of other ongoing construction projects at the time of determining the bid winner.
5. Other key personnel proposed by the bidder shall meet the following requirements:
(1) Design leader: Possess a registered practicing certificate for registered chemical engineers;
(2) Construction leader: Possess a valid electronically registered certificate signed by a registered first-class constructor (in the mechanical and electrical engineering discipline) and a valid safety production assessment certificate (Certificate B) within the validity period;
(3) The bidder shall propose at least one full-time safety production officer who possesses a safety production assessment certificate (Category C);
(4) The key personnel of the project management organization proposed by the bidder (project manager, design leader, construction leader, and full-time safety production officer) shall be personnel of the bidder's own unit. Proof of endowment insurance payment for any one month within the six months prior to the bid submission deadline shall be provided.
Note: The project manager may concurrently serve as the construction leader or design leader, but the construction leader and design leader cannot be the same person.
6. The bidder shall not be listed on the "Dishonest Persons Subject to Enforcement" list on the "Credit China" website, nor on the "List of Enterprises with Serious Illegal and Dishonest Acts" on the National Enterprise Credit Information Publicity System, and shall have no record of bribery crimes as queried on the "China Judgment Documents Network".
7. The bidder shall have sound financial and credit status in the past three years, with sufficient working capital to undertake the bidding project. It shall possess financial statements for the most recent three fiscal years audited by an independent auditing institution, with no property under receivership or frozen, or in a state of bankruptcy due to losses.
8. Different units with the same person in charge or with controlling or management relationships shall not participate in the tender for the same section or the bidding for the same tender project without section division.
This section accepts consortium bidding.
IV. Acquisition of Tender Documents
Acquisition Time: From 21:00 on August 5, 2025, to 21:00 on August 15, 2025
Acquisition Method: Obtain online through the Shanxi Xindian Tendering and Bidding Trading Platform (http://www.sxxindian.com)
V. Submission of Bidding Documents
Submission Deadline: 09:30 on August 27, 2025
Submission Method: Upload the encrypted electronic version of the bidding document to the website (http://www.sxxindian.com) before the submission deadline.
Submission Address: Shanxi Xindian Tendering and Bidding Trading Platform (http://www.sxxindian.com)
VI. Bid Opening Time and Location
Bid Opening Time: 09:30 on August 27, 2025
Bid Opening Method: Online bid opening
VII. Form of Bid Security Submission
For this project, bid security can be submitted in non-cash transaction guarantee methods such as wire transfer, bank guarantee, bond insurance, guarantee institution guarantee, or electronic guarantee.
VIII. Channels and Methods for Raising Objections
Channels for raising objections: via the electronic tendering and bidding trading platform (system)
Contact person for receiving objections: Ms. Shi
Tel: 0351-7815241
IX. Other Announcement Contents
(1) This tender announcement is simultaneously published on the "Shanxi Province Tendering and Bidding Public Service Platform" and the "Shanxi New Point Tendering and Bidding Trading Platform".
(2) The selling price of the bidding documents is as follows (non-refundable): 1,000 yuan. An ordinary invoice will be issued for the bidding document fee, and the tendering agent will send the electronic invoice to the email address provided during bidder registration after the bid opening.
Interested bidders shall upload the "Payment Voucher" and the attached "Mailing Information Form for Bid Award Notice" after paying the bidding document fee to download the bidding documents;
The bank account information of the agency is as follows (only accepting company-to-company account transfers):
Account Name: Shanxi Gemeng Sino-US Clean Energy R&D Center Co., Ltd.
Bank: Pudong Development Bank, Beidajie Branch, Taiyuan City, Shanxi Province
Account Number: 6814 0154 7000 00801
Bank Code: 310161000101
(3) This tender is a fully online tendering project. Bidding entities must register in the Shanxi Province Bidders' Database and obtain a CA certificate for online bidding. (The electronic CA key is not required during the bidding document purchase phase.)
Note: 1. All interested bidders must register in the "Bidding Market Entity Database" section of the National Public Resources Trading Platform (Shanxi Province) (website: http://prec.sxzwfw.gov.cn/). For details, please refer to the registration guide for the Bidding Market Entity Database (website: http://jyzt.sxzwfw.gov.cn/ztxxzc/index.jhtml).
2. If you need to apply for a CA digital certificate, please refer to the "Digital Certificate Cross-Recognition" section of the National Public Resources Trading Platform (Shanxi Province) (website: http://prec.sxzwfw.gov.cn/cajchrpt/).
Consultation hotline for CA certificate application: 0351-6655773
Platform customer service hotline: 0351-8063868
Platform contact person's hotline: 18534576528 (Working hours: 9:00-12:00, 13:30-18:00)
X. Supervisory Department
The supervisory department for this tendering project is Shanxi International Energy Group ESS Co., Ltd.
Tel: 0351-7850578
Email: lijin@gmgjny.com
XI. Contact Information
Tender Inviter: Inner Mongolia Gemeng Yihe New Energy Co., Ltd.
Address: East of Dongmeng East Road, North of Xingba Expressway, Tianpishan Metallurgical and Chemical Industry Park, Chahar Right Wing Front Banner, Ulanqab City, Inner Mongolia Autonomous Region
Contact Person: Mr. Guo
Contact Number: 15525468701
Email: 1962420937@qq.com
Tendering Agency: Shanxi Gemeng Sino-US Clean Energy R&D Center Co., Ltd.
Address: Building 2, Shanxi Gemeng Sino-US Clean Energy R&D Center Co., Ltd. (100 meters east of the intersection of Malianying Road and Zhengyang Street, Taiyuan City)
Contact Person: Ms. Shi
Contact Number: 0351-7815241
Postal Code: 030000
Email: 54400111@qq.com
Source: National Public Resources Trading Platform (Shanxi Province)