In early August, the Baotou Qingyi Jingdian Green Energy Green Electricity Hydrogen Production Project and the Baotou Damao Mengfa Guofu Green Electricity Hydrogen Production Project were approved for filing, with a total project investment of 3.2 billion yuan.
The construction site of the Baotou Qingyi Jingdian Green Energy Green Electricity Hydrogen Production Project is located in the New Industrial Park of Baotou Damao Zero-Carbon Park, Darhan Mumingan United Banner, Baotou City, with a total investment of 3 billion yuan. The project unit is Baotou Qingyi Jingdian Green Energy Technology Co., Ltd.
Construction scale and content: planned construction land area: 34.3890 hectares, construction of green electricity electrolysis water hydrogen production equipment; supporting facilities: hydrogen production plant, compressor plant, circulating water plant, fire pump house, and auxiliary buildings.
Planned construction period: from May 2026 to July 2028.
The construction site of the Baotou Damao Mengfa Guofu Green Electricity Hydrogen Production Project is located in the New Industrial Park of Baotou Damao Zero-Carbon Park, Darhan Mumingan United Banner, Baotou City, with a total investment of 200 million yuan. The project unit is Inner Mongolia Mengfa Guofu Hydrogen Energy Technology Co., Ltd.
Construction scale and content: planned construction land area: 46.6666 hectares, scale: 120,000 Nm³/h green electricity electrolysis water hydrogen production line; supporting facilities: hydrogen production plant, compressor plant, circulating water plant, fire pump house, and auxiliary buildings.
Planned construction period: from July 2026 to June 2028.
Project details are as follows:
Project Filing Notification
Project Code: 2507-150223-04-01-415465
Project Unit: Baotou Qingyi Jingdian Green Energy Technology Co., Ltd.
The industrial project filing (NDRC) for the Baotou Qingyi Jingdian Green Energy Green Electricity Hydrogen Production Project submitted by you complies with industrial policies and market access standards and is approved for filing. Please carry out relevant work accordingly. Before commencing construction, other procedures required by laws and regulations shall be completed before construction can begin. This is hereby notified!
Construction site: New Industrial Park of Baotou Damao Zero-Carbon Park, Darhan Mumingan United Banner, Baotou City
Total investment: 3 billion yuan, including 600 million yuan of self-owned funds, 2.4 billion yuan of bank loans applied for, and 0 yuan of other funds.
Planned construction period: from May 2026 to July 2028.
Construction scale and content: planned construction land area: 34.3890 hectares, construction of green electricity electrolysis water hydrogen production equipment; supporting facilities: hydrogen production plant, compressor plant, circulating water plant, fire pump house, and auxiliary buildings.
Supplementary instructions: The project unit shall incorporate the awareness of building a strong sense of community for the Chinese nation into the project implementation; strictly comply with laws and regulations such as the "Work Safety Law" and establish and improve various work safety systems; promptly upload energy-saving declaration forms or energy-saving reports through the online platform, and truthfully report basic information on project commencement, construction progress, and completion.
(Note: If the project has not commenced construction or undergone any other procedures within two years from the date of filing, and the project unit decides to continue with the project, please provide an explanation via the online platform. If the project unit decides not to continue, please apply for the cancellation of the filed project. If no explanation is provided and the project is not cancelled within two years, the filing authority will delete the filed project and announce it on the online platform.)
Darhan Muminggan United Banner Development and Reform Commission
August 4, 2025
Project Filing Notification
Project Code: 2507-150223-04-01-434974
Project Unit: Inner Mongolia Mengfa Guofu Hydrogen Energy Technology Co., Ltd.
The industrial project filing (NDRC) for the Baotou Damao Mengfa Guofu Green Electricity Hydrogen Production Project you submitted complies with industrial policies and market access standards, and is hereby approved for filing. Please proceed with relevant work accordingly. Before commencing construction, other procedures required by laws and regulations must be completed.
Construction Location: New Industrial Park, Baotou Damao Zero-Carbon Industrial Park, Darhan Muminggan United Banner, Baotou City
Total Investment: 200 million yuan, including 80 million yuan of self-owned funds, 120 million yuan of bank loans, and 0 yuan from other sources
Planned Construction Period: From July 2026 to June 2028
Construction Scale and Content: Planned construction land area: 46.6666 hectares; scale: 120,000Nm³/h green electricity electrolysis water hydrogen production line, supported by hydrogen production plants, compressor plants, circulating water plants, fire pump houses, and auxiliary buildings.
Supplementary Notes: The project unit shall incorporate the awareness of building a strong sense of community for the Chinese nation into the project implementation; strictly comply with laws and regulations such as the "Work Safety Law" and establish a sound work safety system; promptly upload energy-saving declaration forms or energy-saving reports via the online platform, and truthfully report basic information on project commencement, construction progress, and completion.
(Note: If the project has not commenced construction or undergone any other procedures within two years from the date of filing, and the project unit decides to continue with the project, please provide an explanation via the online platform. If the project unit decides not to continue, please apply for the cancellation of the filed project. If no explanation is provided and the project is not cancelled within two years, the filing authority will delete the filed project and announce it on the online platform.)
Darhan Muminggan United Banner Development and Reform Commission
August 1, 2025