Hebei Provincial Flood Control and Disaster Relief and Post-Disaster Reconstruction Press Conference was held in Shijiazhuang. According to the data released at the meeting, as of August 10, there were 2,470 blocked roads in Hebei Province, and 2,237 of them had been restored. 1,723 10 kV power lines had been out of service, and 1,631 lines were repaired. Among them, 22 of 13 damaged 35-kV lines were repaired, and 3,563 of 4,251 decommissioned physical base stations were repaired. Those that have not yet been restored are being repaired with all strength.
Hebei: 2,237 blocked roads have been restored
- Aug 11, 2023, at 5:52 pm
Hebei Provincial Flood Control and Disaster Relief and Post-Disaster Reconstruction Press Conference was held in Shijiazhuang.



