The second phase of the relocation and upgrading project of copper smelting technology at Chifeng Jintong Copper Co., Ltd. is currently underway with the pile foundation construction of the second-phase sampling center. So far, 20 piles have completed their concrete pouring. The project is expected to complete all civil, decoration, and water and electricity works by October 10, 2025, meeting the conditions for the owner's relocation and use.